Council briefs: North Battleford approves arena spending and road repairs
North Battleford city council has approved another $305,400 for its proposed twin-pad arena and events centre, with a revised estimate of the project’s overall cost still to be presented publicly.
The allocation approved Oct. 13 covers payments of $150,000 each to two unsuccessful design-build bidders, plus $5,400 in provincial sales tax.
City Manager John Enns-Wind said three firms have been shortlisted. Preparing a proposal could cost each team $200,000 to $300,000, meaning the payments would cover only part of that expense.
The payments would depend on proposals meeting the city’s requirements. In exchange, the city would retain rights to concepts, innovations and design approaches from the unsuccessful submissions.