North Battleford’s 110th Street infrastructure work on track for August completion
North Battleford’s underground pipe and asphalt replacement (UPAR) project remains on track to finish by the end of the month, according to the city’s latest public update.
Jaime Garcia, UPAR project manager, said crews have already installed about 780 metres of new PVC water and sewer mains, along with all service line replacements for residents who opted in. Concrete work began last week, with paving to follow shortly afterward.
“We could almost see the end of the project that would be completed this month,” Garcia said.
He added the project remains on schedule, with underground work completed by the July 31 target date.