City to upgrade Don Ross Arena ice plant
North Battleford city council has approved replacing the Don Ross Arena ice plant that is in need of work.
City Fleet and Maintenance Manager Seton Winterholt gave a report on the issue at this week’s council meeting.
Administration recommended awarding the Don Ross Arena ice plant replacement contract to Canadian Climate Refrigeration and HVAC, in the amount of $766,559 (PST included). It also advised creating a $200,000 contingency fund for any unforeseen construction costs related to the project, for a total cost of about $966,559.
The city budgeted $1.2-million for the total project, so it should come in under budget.