Click here to sign up for our free daily newsletter
ID 31259376 © Blazej Lyjak | Dreamstime.com
2025 UPAR UPADTES

City 110th Street project to start sidewalk, paving work in August

Jul 30, 2025 | 2:13 PM

Underground work on 110th Street is nearly complete, and the city says the project will move to sidewalks and paving in August.

As of July 22, work crews have replaced about 625 metres of water and sanitary sewer mains, out of a total 780 metres planned for the project.

With the underground phase set to finish by the end of July, concrete work on sidewalks is expected to begin in early August, followed by asphalt paving shortly after.

Additional sidewalk projects across the city will also get underway once concrete contractors arrive after the long weekend.