NB Sanitary Sewer Trunk upgrade engineering costs see increase
The City of North Battleford’s Primary Sanitary Sewer Trunk upgrade project will be dealing with more increased costs.
Council heard at this week’s meeting engineering services are estimated to run up to $90,000 more than anticipated due to several factors.
Project engineering firm AECOM Canada Ltd. was hired to do the engineering work for the sanitary force main sewer system project and the sewage pumping station.
AECOM indicated the contractors’ schedules and productivity were not in line during the 2021 construction period, as Hamm Construction started in the spring of 2021 while the Con-Tech construction team did not mobilize until the fall of that year, which affected costs. As well, both firms’ crews were impacted by the COVID-19 pandemic, which resulted in additional engineering costs.